What Is a Notice of Readiness and When Does Laytime Start?

Published: 4 min read

A notice of readiness (NOR) is the written notice by which the master or agent informs the relevant parties that the vessel has arrived at the place specified in the charter party and is ready in all respects to load or discharge. As a rule, laytime starts to run after a valid NOR has been tendered and any contractual notice time has expired.

Why is the NOR such an important document?

Under voyage charters, time spent in port translates directly into money between the parties. The charter party allows a set period, laytime, for loading and discharging. If it is exceeded, charterers pay demurrage to owners; under some contracts, if cargo work finishes early, owners pay despatch to charterers.

The starting point of that calculation is usually the NOR, so when, how and to whom it was tendered shapes the laytime statement that follows. Every charter party has its own wording, so what follows describes general concepts; in any real case, the charter party itself governs.

What makes a notice of readiness valid?

On the generally accepted view, several conditions must be met together for an NOR to be valid. If one of them is missing, the notice may be invalid and laytime may not start.

The conditions most often required are:

  • The vessel has reached the place named in the charter party (arrived ship)
  • The vessel is ready in all respects: holds clean and suitable, gear in working order
  • Health and customs clearances are obtained, unless the contract says otherwise
  • Notice is tendered on the days and at the hours the contract allows
  • Notice is given in the agreed manner and to the right parties
Field team reviewing the operation plan alongside a vessel at a container terminal

What is the difference between a berth charter and a port charter?

Where a ship counts as arrived depends on the type of charter. Under a berth charter, the vessel arrives only on reaching the nominated berth, so time spent waiting for the berth is in principle at owners' risk. Under a port charter, reaching a point within the port where the vessel is at the charterers' disposal may be enough.

The parties often reallocate that risk with standard phrases. The most common abbreviations are:

  • WIBON: whether in berth or not
  • WIPON: whether in port or not
  • WIFPON: whether in free pratique or not
  • WCCON: whether customs cleared or not

When exactly does laytime start?

Commencement of laytime depends on the charter party wording. Many contracts provide for a notice time after the NOR is tendered, with laytime starting once it has expired. The widely used version of the GENCON form, for instance, sets different commencement times depending on whether notice is given before or after noon.

Rider clauses can change these rules. Some contracts provide that if work starts before notice time expires, time counts from the actual commencement of work. Laytime commencement should therefore be read from the standard form and the riders together.

Which terms are used in laytime calculations?

Laytime calculations rely on abbreviations that define which days and hours count. SHINC means Sundays and holidays included; SHEX means they are excepted. Under a weather working day basis, periods when work is prevented by weather do not count.

Once laytime is exceeded, demurrage runs, usually at a daily rate pro rata. The despatch rate is also set by contract and is commonly agreed as a fraction of the demurrage rate, often half. The maxim once on demurrage, always on demurrage is frequently applied unless the contract provides otherwise.

What happens if the NOR is invalid?

An invalid NOR can mean laytime never starts, or starts later than expected, which may reduce or remove the demurrage owners anticipated. To manage that risk, masters often re-tender notice as conditions change or tender a further NOR without prejudice to earlier ones.

Whether unconditional acceptance of a defective NOR by charterers changes the outcome has been treated differently across legal systems and cases. Where a dispute over NOR or laytime arises, it should be assessed on the charter party wording and with legal advisers.

What is the port captain's role in the NOR process?

The master tenders the NOR; the port captain helps make sure the process is properly recorded on behalf of the principal. The port captain independently notes arrival, anchoring and berthing times, whether the holds are ready, and when notice was tendered and accepted.

These records allow a comparison with the statement of facts and the laytime calculation after completion. Karan Gözetim can keep such time records as part of its port captain service from Gemlik, with the scope agreed at the quotation stage.

Frequently asked questions

Can a notice of readiness be sent by email?

That depends on the charter party. Many modern contracts expressly allow email; some older forms provide for other means of transmission. What matters is that notice is sent by the contractual method and to the correct recipients.

What is free pratique?

Free pratique is clearance from the port health authority confirming that the vessel may have contact with the shore. Some charter parties require it before NOR can be tendered; the phrase WIFPON relaxes that requirement.

Are laytime and laycan the same thing?

No. Laycan is the date range within which the vessel must arrive at the load port. Laytime is the time allowed for loading or discharging once the vessel has arrived. They are separate concepts dealt with in separate clauses.

Topics

  • notice of readiness
  • what is NOR in shipping
  • when does laytime start
  • laytime and demurrage
  • WIBON meaning
  • arrived ship

Get a quote for Port Captain

Send us the vessel, port, cargo and the service you need; we will define the scope with you and prepare a quotation.

Message us on WhatsApp (WhatsApp opens in a new tab)