Skip to content
KARANGÖZETİM VE DANIŞMANLIK

Loading and Discharge Supervision

What Is a Statement of Facts and How Does It Drive Laytime and Demurrage?

Published: 4 min read

A statement of facts (SOF) is the port document that lists, with dates and times, every significant event from a vessel's arrival to its departure. It is normally prepared by the agent and signed by the master and the other parties involved. Because laytime, demurrage and despatch are calculated directly from it, every line of the SOF can carry a commercial consequence.

What does a statement of facts record?

Formats vary between ports and agents, but the events recorded are broadly similar. Each event is entered with start and finish times, and every stoppage should carry a stated reason.

  • Arrival at anchorage or at the berth
  • Notice of readiness tendered and accepted
  • Free pratique and other formalities
  • Pilot on board and all fast
  • Hold inspection and its outcome
  • Commencement and completion of loading or discharge
  • Stoppages for rain, equipment breakdown, awaiting cargo and similar
  • Draft survey times and documents on board

What are laytime, demurrage and despatch?

Laytime is the time allowed to the charterer under the charter party for loading or discharging. It may be expressed as a daily rate of cargo handled or as a fixed number of days. When laytime commences, which days count and which events interrupt it are also defined by the contract.

If the operation exceeds the time allowed, the charterer pays demurrage to the owner. Where the contract provides for it, the owner pays despatch to the charterer for time saved. Because both are calculated from SOF times, a discrepancy of a few hours can translate into a significant sum.

Bulk carrier being loaded by crane and hopper at the quay, with port personnel working on the berth

Which charter party terms change how time counts?

Charter parties rely on standard abbreviations. WWD (weather working day) means only days on which weather permits work are counted; SHINC means Sundays and holidays are included, while SHEX means they are excepted.

For this reason the SOF must record not just the duration of a stoppage but its true cause. Hatches closed because of rain and a breakdown of terminal equipment may be treated quite differently under the same contract.

What problems do SOF errors cause?

Typical weaknesses include vague stoppage descriptions, partial stoppages that are not recorded at all (for example, one hold idle while others work) and times that do not match across documents. Omitting facts that could affect the validity of the notice of readiness, such as holds failing inspection, also leads to disputes.

These gaps usually surface months later, when a demurrage claim is presented. By then it is rarely possible to reconstruct what was not written down at the time.

Time zone and date errors are another trap. Failing to state whether ship's time or local time is used, or booking a stoppage that runs past midnight to the wrong day, creates deviations that are easy to miss in the calculation.

What should be checked before signing the SOF?

Before signing, SOF times should be cross-checked against independent records kept on site. Where a party disagrees with an entry, signing the document under protest or attaching a separate letter of protest is common trade practice.

How a protest should be made and what effect it has depends on the contract and the facts, and the parties should take their own advice on it. What matters in practice is that the protest is made during or immediately after the operation and supported by concrete records.

How does the notice of readiness start laytime?

Laytime generally cannot start until the vessel is an arrived ship and ready in all respects to load or discharge. At that point the master or agent tenders the notice of readiness (NOR). The charter party may provide for laytime to commence after a set period following tender or acceptance.

Whether the vessel must reach the berth or merely the port to count as arrived depends on whether it is a berth or a port charter. Wording such as WIBON (whether in berth or not) allows notice to be tendered even when no berth is free. The times of tender and acceptance are therefore among the most critical entries in any SOF.

How do independent time logs support the SOF?

During loading and discharge supervision, the surveyor logs commencement, stoppages and completion together with their causes. These logs form an independent data set that can be compared line by line with the agent's SOF.

Karan Gözetim, based in Gemlik, keeps this type of time log as part of its loading and discharge supervision; the level of detail is agreed at the quotation stage.

Frequently asked questions

Is a statement of facts the same as a time sheet?

No. The SOF records events chronologically. The time sheet, or laytime calculation, uses those events to work out which time counts and which does not, and is normally prepared on the basis of the SOF.

How should partial stoppages be recorded?

Where only some holds or cranes are idle, the SOF should state which holds or equipment were affected and for how long. Depending on the contract, this can have a pro rata effect on the time counted.

When does a demurrage claim usually arise?

Normally after the operation, once the laytime calculation is prepared. Time limits for notifying and documenting claims are often set in the charter party, which is why complete records during the operation matter.

Topics

  • statement of facts
  • statement of facts shipping
  • laytime calculation
  • demurrage and despatch
  • notice of readiness
  • weather working day
  • SOF signed under protest

Get a quote for Loading / Discharge Supervision

Send us the vessel, port, cargo and the service you need; we will define the scope with you and prepare a quotation.

Message us on WhatsApp (WhatsApp opens in a new tab)