Skip to content
KARANGÖZETİM VE DANIŞMANLIK

Draft Survey

What Is a Draft Survey and How Is It Carried Out Step by Step?

Published: 5 min read

A draft survey is a method of establishing the weight of cargo loaded or discharged by reading a vessel's draught marks, calculating her displacement before and after the operation and taking the difference. It is based on Archimedes' principle and is widely used in dry bulk trades where shore scale figures are unavailable or need independent verification.

What principle is a draft survey based on?

A floating body displaces a weight of water equal to its own weight. As a ship takes on cargo she sinks deeper, and her displacement increases with her draught. The vessel's hydrostatic tables, produced by the shipyard, give the displacement corresponding to each draught.

The draft survey uses this relationship by establishing the total weight of the ship at the start and at the end of the operation. Once the non-cargo variable weights are deducted, the difference between the two figures is the weight of cargo loaded or discharged.

When is a draft survey the preferred method?

The method is standard for large, homogeneous dry bulk parcels such as iron ore, coal, grain, fertiliser and clinker. It becomes particularly important where there is no shore scale, where the accuracy of a belt weigher is disputed, or where the sales contract calls for an independent determination of quantity.

For bagged, unitised or break bulk cargo, quantities can usually be tracked by piece count and unit weight, so draft surveys are used less often. For small parcels the measurement uncertainty can be large relative to the cargo quantity, so the suitability of the method should be considered case by case.

Bulk carrier berthed at the quay with port cranes at sunset

What happens during the initial survey?

The initial survey takes place before cargo operations begin. The surveyor and the ship's officers read the six draught marks together, take a dock water sample to measure density and sound the ballast, fresh water and bunker tanks.

The vessel's constant is also established at this stage. The constant represents unrecorded weights on board, the difference between the light ship plus known weights and the measured displacement, and is treated as unchanged for the rest of the calculation.

  • Reading forward, aft and midship marks on both port and starboard sides
  • Measuring dock water density with a hydrometer
  • Sounding ballast, fresh water and bunker tanks
  • Deriving displacement from the hydrostatic tables and calculating the constant

How is the final survey used to calculate cargo quantity?

When loading or discharging is complete, the same procedure is repeated. Trim, deflection and density corrections are applied to the observed draughts to obtain the corrected displacement, and the deductibles such as ballast, fresh water and bunkers are subtracted.

On loading, the initial net weight is subtracted from the final net weight; on discharge the calculation is reversed. The result is the ship's figure for the cargo, which is normally compared with the B/L figure or the shore scale weight.

When is an interim survey needed?

An interim draft survey may be carried out during long loading operations, where a cargo is split between several receivers or bills of lading, or where the loading plan requires a stop at a specific tonnage. It shows whether the operation is progressing towards the intended quantity.

Interim readings near the end of loading also help plan the final trimming pours, so that the vessel reaches her target draught and trim in a controlled way rather than by trial and error.

Which basic terms come up in a draft survey?

A handful of concepts is enough to follow the method. They appear throughout the report and in discussions with the ship's officers, and knowing them makes it easier to see what each stage of the calculation is doing.

The distinction between the constant and the deductibles matters most. Deductibles are measured afresh at every survey, whereas the constant is calculated once at the initial survey and assumed not to change during the operation.

  • Displacement: the total weight of the vessel, equal to the weight of water she displaces
  • Light ship: the weight of the empty vessel without bunkers, water, ballast, cargo or stores
  • Deadweight: the total of cargo, bunkers, water and other variable weights the vessel can carry
  • Deductibles: ballast, fresh water, bunkers, lube oil and other weights subtracted at each survey
  • Constant: unrecorded weights on board that are treated as fixed

What does a draft survey report contain?

The report records the observed draughts, dock water density, tank soundings, the corrections applied, the constant and the calculated cargo quantity. Weather, swell and current at the time of the readings, and any observations that may have affected accuracy, are noted as well.

Having the report countersigned by the ship's officers shows that the survey was carried out jointly and reduces the scope for later objections. Karan Gözetim provides draft survey services from its base in Gemlik; the scope of work and the party the report is issued to are agreed at quotation stage.

Frequently asked questions

Is a draft survey the same as weighing the cargo?

No. A draft survey is a calculation derived from the vessel's draught rather than a direct weighing. Carried out carefully in suitable conditions it gives a reliable quantity, but there is always some uncertainty depending on the survey conditions.

How long does a draft survey take?

It depends on the size of the vessel, the number of tanks, weather and sea conditions and how well the crew has prepared. Tanks that are pressed up or empty and documents that are ready to hand make the survey considerably faster.

Can draft surveys be carried out at both load and discharge ports?

Yes. Surveys at each port are independent of one another, and comparing the results is a common way of assessing alleged in-transit shortages or surpluses.

Topics

  • what is a draft survey
  • how is a draft survey done
  • draft survey procedure
  • draught survey steps
  • displacement calculation
  • bulk cargo quantity determination

Get a quote for Draft Survey

Send us the vessel, port, cargo and the service you need; we will define the scope with you and prepare a quotation.

Message us on WhatsApp (WhatsApp opens in a new tab)